Hillside Pavilion at dusk, a glass living floor set over a concrete base on a sloped Los Angeles lotHillside home design
Service

Hillside home design in Los Angeles

A sloped lot sets its own rules: how much house, how much earth moved, and which reports the city reads before it issues a permit.

What a hillside lot changes

A flat lot starts with the zoning envelope. A hillside lot in Los Angeles starts with the slope. The slope sets how much floor area the house may have, how much earth can be moved, how the foundation reaches firm ground and which reports the city reviews before it issues a permit. TECTO Studio designs houses for these lots and takes them to the issued permit, at a fixed fee agreed up front.

The Baseline Hillside Ordinance

In the City of Los Angeles, single-family lots zoned R1, RS, RE or RA inside a designated Hillside Area follow the Baseline Hillside Ordinance (BHO). City Planning describes it as a limit on residential floor area and on grading based on lot size, first adopted in 2011 under Ordinance 181,624 and amended in 2017 under Ordinance 184,802. A lot is subject to it when the ZIMAS property profile shows Zoning Information ZI-2462 (City Planning fact sheet).

The LADBS Baseline Hillside Ordinance correction sheet shows what plan check looks for:

  • Floor area by slope. The maximum residential floor area comes from a slope analysis. The plans need a Slope Analysis Survey and a Slope Band Analysis form approved by City Planning, unless the house stays within the minimum floor area the code allows every lot.
  • What counts as floor area. Attic space with a ceiling over 7 feet counts. Space with a ceiling over 14 feet counts twice. A basement counts when the floor above it sits more than 3 feet above grade along more than 60 percent of its perimeter.
  • Long side walls. In the R1 zones, a side wall taller than 14 feet and 45 feet or longer needs a break at least 5 feet deep and 10 feet long.
  • One bonus. RA, RE and RS lots may use one floor area bonus, such as the proportional stories option, where each upper story is at most 75 percent of the base floor.

Some hillside communities, such as Bel Air, Beverly Crest and Laurel Canyon, also fall under the Hillside Construction Regulations, a supplemental use district with its own grading, hauling and construction-hour limits (City Planning fact sheet). The mansionization guide covers the floor area rules for lots outside the Hillside Area.

Grading limits

Earth moved on a hillside lot is capped. Under Code Section 12.21 C.10-6, the by-right maximum in the R1 zone is 1,000 cubic yards, with some exemptions. Grading beyond the limit needs a Conditional Use Permit from a Zoning Administrator under Section 12.24 X.28 (City Planning fact sheet). The other R zones have their own limits in Table 12.21 C.10-6.

The LADBS single-family plan check correction sheet adds the steps that follow from grading in the Hillside Grading Area:

ConditionWhat LADBS asks for
Foundation or grading workA copy of the grading pre-inspection report, with its conditions met
More than 500 sq ft of new floor areaPosting notification, with notices mailed 10 days before the permit is issued
More than 250 cubic yards of soilA grading bond
More than 1,000 cubic yards imported or exportedA haul route application and a public hearing, with a minimum of eight weeks to process

The design tries to balance cut and fill on the site, so less soil leaves or arrives by truck.

Soils, geology and retaining walls

Before LADBS issues permits for grading in the Hillside Grading Area, a soils and/or geology report is usually submitted to the Grading Division for review. The reports address the foundation design and geologic hazards such as slope instability, earthquake-induced landslides and liquefaction (LADBS Grading). The single-family correction sheet asks for the approved report and the approval letter, and for plans that show compliance with both.

The soils engineer's recommendations set the foundation: how deep the footings go, how far they sit from the face of the slope, and what kind of foundation the ground needs. Plan check reviews retaining walls, grading and shoring with a supplemental correction sheet of their own, listed on the single-family correction sheet.

A house that steps with the slope

A hillside house works best when it follows the ground. Floors step down the slope, so each level meets the grade at some point and less earth is cut. The living floor sits where the view is, and the garage stays near the street. A concrete base holds the hill, and a lighter structure sits on top of it.

TECTO Studio works through the slope with the site survey and the soils report from the first plan. The structural engineer and the soils engineer are brought in early, because the foundation and the walls shape the plan as much as the rooms do. The permit set brings the drawings, the structural sheets and the approved reports into one coordinated filing; see single-family permits.

Lucas Rebouças leads every house, with ten years in residential design and permitting in Los Angeles and more than 100 projects across single-family and multifamily. See Los Angeles.

Tell us about your lot.

lucas@tecto.studio  ·  310-490-7219

Send the address, what you want to build and when. Lucas replies with a scope, a fixed fee and the steps to the permit.