What a custom home costs to design, permit and build in Los Angeles
Land, soft costs, city fees, utilities and construction, with a worked example built only from published unit figures.
The five parts of the budget
A custom home budget in the City of Los Angeles has five parts. Each one is set by a different party, at a different time.
- Land. The lot, its price and its closing costs.
- Soft costs. Design, structural engineering, the Title 24 energy report, and soils, geology and survey work where the site needs them.
- City fees. Plan check and permit fees from the Department of Building and Safety (LADBS), school fees, and other fees that apply to new homes.
- Utility connections. Water, power, gas and sewer service to the new house.
- Construction. The builder's price to build the house, usually the largest line.
This guide covers parts two to five. It gives figures only where a public agency or a named published source states them, with the source and its date.
Land
Land is outside the scope of this guide. The price of a lot depends on its neighborhood, size, slope and access, and it is usually settled before design starts. Two things about the lot do shape the other four costs: its zoning, which limits the size of the house, and its site conditions, which decide which consultants the permit set needs.
Soft costs: design and consultants
Soft costs are the fees for the drawings and reports the city reviews. Each one is quoted per project, so this guide gives no figures for them.
- Design. The designer draws the house, from the zoning study to the permit set, and answers plan check comments.
- Structural engineering. The structural engineer designs the foundation, the framing and the lateral system, and signs the structural sheets and calculations.
- Title 24 energy. California's energy code requires a compliance report for every new house. An energy consultant usually prepares it.
- Soils and geology. A soils report sets the foundation design. In the City of Los Angeles, a geology and soils engineering report is required in hillside, seismic and liquefaction areas when construction is proposed, per the City's SB 9 implementation memo of August 24, 2026, which cites LADBS Information Bulletins P/BC 2023-129 and P/BC 2023-044.
- Survey. A boundary and topographic survey is the base for the site plan on most lots.
Ask for each consultant's scope in writing: what the fee includes, how many rounds of plan check comments it covers, and what counts as extra work.
City fees
LADBS plan check and permit fees. LADBS states that building permit fees are calculated based on the valuation of the project, under Los Angeles Building Code section 91.107. A larger or more costly house has a higher valuation and pays higher fees. LADBS publishes a fee estimator for a first figure; the final amount is set at plan check.
School fees. The Los Angeles Unified School District charges a school impact fee on new residential construction. Its rate is $5.38 per square foot, effective August 11, 2026, up from $5.17, after the LAUSD Board approved a new fee study on June 12, 2026.
Affordable Housing Linkage Fee. The City charges this fee on certain new residential floor area. The City Planning implementation memo of April 22, 2026 states that a single-family home can be fully or partly exempt: new or added floor area under 1,500 square feet is exempt in the cases it lists, and some additions and replacement homes over 1,500 square feet are exempt if the home stays under the same ownership for three years from permit issuance. If the fee applies, all net new floor area is charged. The fee schedule effective July 1, 2025 sets the single-family rate at $10.32, $12.90, $15.47 or $23.20 per square foot, by market area. The rates adjust for inflation each July 1, and the project pays the rate in place when the building permit is issued, so confirm the current rate for your lot.
Utility connections
A new house needs water, power, gas and sewer service. In most of the City, water and power come from the Los Angeles Department of Water and Power. Connecting a house sewer to a City sewer takes a written permit from the Board of Public Works, issued on payment of the permit charges, under Municipal Code section 64.12. Connection costs depend on the size of the service, the distance to the main and the work in the street, so each utility quotes them per project. Budget a separate line for them and request the quotes early.
Construction cost per square foot
Builders price a house from the drawings, so the only firm construction figure is a bid on a finished set. Before that, a published valuation table gives a reference point.
The International Code Council publishes Building Valuation Data, a table that, in the ICC's words, provides "average" construction costs per square foot that can be used in determining permit fees. The full table is for ICC members. The City of Irvine publishes a building valuation table effective August 15, 2026, set on the basis of the ICC table. For one- and two-family dwellings (occupancy R-3), it lists:
| Construction type | Cost per square foot |
|---|---|
| Type V-A | $187.70 |
| Type V-B | $175.92 |
| Utility, miscellaneous (U), Type V-B | $71.07 |
Type V is the wood-frame construction type in the building code. The U row covers garages and similar structures.
These are average valuation figures for permit fees. A real bid in Los Angeles can be well above or below them. The finish level, the amount of glass, the structure, a basement or a slope, the access to the site and the market at the time of bidding all move the price.
A worked example: 3,000 square feet
The table below is an example only. It applies the published unit figures above to a 3,000 square foot house with a 400 square foot garage on a flat lot in the City of Los Angeles. It does not estimate any real project.
| Item | Unit figure and source | Example amount |
|---|---|---|
| House, R-3, Type V-B, 3,000 sq ft | $175.92 per sq ft, Irvine table, Aug. 15, 2026 | $527,760 |
| Garage, U, Type V-B, 400 sq ft | $71.07 per sq ft, Irvine table, Aug. 15, 2026 | $28,428 |
| LAUSD school fee, 3,000 sq ft | $5.38 per sq ft, LAUSD, Aug. 11, 2026 | $16,140 |
| Linkage fee, 3,000 sq ft, if it applies | $10.32 to $23.20 per sq ft, City schedule effective July 1, 2025 | $30,960 to $69,600 |
The example leaves out land, design and consultant fees, LADBS plan check and permit fees, utility connections, and any site work beyond the house. Each of those has to be added from quotes and from the LADBS fee estimator.
Design and permits with TECTO Studio
TECTO Studio designs custom homes in Los Angeles, from the first plan to the issued permit, at a fixed fee agreed before the work starts. The plan options are drawn with the budget in view, since the structure, the glass and the shape of the plan drive construction cost. See custom home design, the permit steps guide and the studio's work in Los Angeles.